Boac DPP info on current power outages

Info received today from Boac Diesel Power Plant (DPP) which is under NPC Supervision:

"Delivery of Bunker Fuel will commence today at 1300 HR in Power Barge 120. In view of this development, we will operate the Power Barge 24 hours with an estimate load capacity of 4.5MW with rotational load schedule that will start today Feb. 4 up to Feb. 25, 2011. Boac DPP will operate only during peak hours from 5:00pm to 11:00pm."

No comments:

Post a Comment

Followers