Marelco informs that based on “Fuel Run Out Dates of NPC-SPUG” furnished by the Department of Energy (DOE) to the electric cooperative there will be an impending power interruption in Marinduque. Marelco, however, states that Marinduque NPC-SPUG based in Bantad has informed them that power interruption could take place beginning today (as it already has), “because of a defective unit at Power Barge 120” at Balanacan harbor.
It will be recalled that in May this year, Marelco announced that it published in March 2011, an invitation for bidders to participate in the bidding for the supply of a brand new Modular Type Diesel Hybrid Power Plant in Marinduque. Bidders were to have a capacity to initially deliver more or less 3,000,000 kwh per month to the Marelco system. During the annual membership meeting in May, it was then announced that at least three bidders have applied for eligibility and participated in the bidding.
According to Marelco’s schedule of activities, opening of bids and comparison with Best New Entrant Rate (BNER), was scheduled to take place last July 8. Negotiation and Award of a Power Supply Agreement (PSA), is to take place on August 9, 2011, with award of contract and issuance of Notice to Proceed (NTP), taking place on September 5, 2011. This new agreement is also to specify that commercial operation by the new power provider is to commence after 270 days from the award of contract - that is, by June 2012. No update on this matter has been released by Marelco, so far.
From the looks of it, therefore, the island-province of Marinduque is in for another year of power uncertainties during this transition period unless effective intervention is undertaken by the energy authorities now, repeat, now...
No comments:
Post a Comment